wiki:docs/CommissioningPlan

Version 66 (modified by kradhakrishnan, 4 years ago) (diff)

--

SHARK-NIR Commissioning Plan

This commissioning planning document lays out and details the activities needed to bring SHARK-NIR online for regular scientific exploitation. The document incorporates activities starting from the unpacking of the boxes at the LBT mountain bay to the early science /science verification at its final destination on the LBT platform. Although called the commissioning document, it lists the pre-commissioning, commissioning, and science verification activities.

The commissioning is broadly divided into four phases:

Phase 1: We start by inspecting the boxes at LBT mountain bay, unpacking, and installing the instrument at the mountain lab (clean room) for alignment verification and functionality checks. All of these are daytime activities. [Pre-commissioning: Unpack, assemble, and clean-room verification]

Phase 2: The activities starting from the installation of SHARK-NIR at the SX central bent Gregorian focus of LBT, followed by preliminary functional checks, aligning SHARK-NIR to the telescope (daytime), and daytime closed dome engineering/technical testing. All of these are daytime activities. [Pre-commissioning: Installation & Closed-Dome Testing]

Phase 3: Phase 3 commences the nighttime commissioning, starting from sending preset to the telescope to testing individual SHARK-NIR observation modes for performance to the total SHARK-NIR performance. All the activities are nighttime. However, some daytime activities may be anticipated as well. By the end of this phase, SHARK-NIR is ready for early science observations. [Commissioning]

Phase 4: SHARK-NIR is ready for the final phase of the commissioning - the science verification / early science observations. The final form of the SHARK-NIR software, observing blocks, data-reduction pipeline, etc. will be tested for all the modes (and sub-modes) of the instrument. The final performance of the SHARK-NIR will be analyzed using the data from this run. All the activities are nighttime. By the end of this phase, SHARK-NIR is ready for regular science operations (with some 'risk' of course for another year). [Science Verification / Early Science]

Note that the corresponding evolving doc in the SHARK-NIR Dropbox folder is SHARK-NIR-INAFP-COM-001_CommissioningPlan.docx. There is also an excel file listing the activities titled SHARK-NIR-INAFP-COM-002_CommissioningActivityList.xlsx (BOTH NOT UPDATED).

Applicable Documents (needs update)

No. Title Number & Issue
AD1 SHARK-NIR Schedule SHARK-NIR-INAFP-SCH-001_Issue 1.2.pdf
AD2 SHARK-NIR SW ICD SHARK-NIR-INAFP-SW-ICD-FDR Issue 0.4
AD3 SHARK-NIR Installation Plan SHARK-NIR-INAFP-IP-001 Issue 0.2
AD4 SHARK-NIR Calibrations SHARK-NIR-INAFP-MAN-004

Category

The table below lists the categories of commissioning activities.

Category NameCategory Number
Installation, integration, verification (Pre-commissioning) C1
Daytime testing (functionality and operability)C2
Daytime calibrationC3
Nighttime testing (functionality and operability)C4
Nighttime Science CalibrationC5
Nighttime testing for performanceC6

Naming structure of the commissioning activity

Each commissioning test/activity has a unified structure as follows:

Name of the commissioning activity
  - phase : states the phase of the commissioning (1/2/3/4)
  - status : reports the current status of the test (draft, final, complete)
  - category : one of the categories mentioned above
  - recurrence : describes how frequently the test must be executed
  - duration : estimates the time required to complete the test (the duration mentioned here is valid only for commissioning)

Description
  - Contains a general description of the test

Prerequisites
  - Lists items that must be in place before the test begins

Procedure
  - Explains in detail how to execute the test

Success Criteria
  - Enumerates the outcome associates with successful completion of the test

Notes
  - Additional supporting information

LBTO Support
  - Mention if (and what) support required from LBTO

Associated SHARK-NIR personnel
  - Mentions here who are the associated personnel to the test

Date performed and by whom
  - Mentions who performed the test and when

Commissioning Activity

In this section, you can see all the commissioning activities listed in chronological order. If you click the individual activity, you can see more details of it.

Phase 1 (Pre-commissioning)

SHARK-NIR Location : LBT mountain bay and clean room (Some of the activities may run in parallel). All daytime activities.

NumberActivity NameDay / NightDuration (days)CategoryLBTO Support
P1.1Inspection of the boxesDay0.5C1crane operator to lift and move containers/boxes (mountain bay)
P1.2Opening boxes and their visual inspectionDay0.5C1crane operator to lift and move containers/boxes (mountain bay), 1-2 crew to support unpacking and moving
P1.3Install the instrument in the cleanroom with its electronics cabinetDay0.5C1crane operator to lift and move containers/boxes (mountain bay & cleanroom), 1-2 crew to support installation on the mechanical structure
P1.4Cable in the instrument, power on, install workstations, and connect to LBT networkDay0.5C1support to connect to LBT network, IT support to install/set the workstations in the proper location
P1.5Start all the services and initialize all the motorsDay0.5C1-
P1.6Cool down the cryostatDay1C1Liquid N2 fill in the cleanroom
P1.7Verification of the operability of the motors and light sourcesDay0.5C1optical bench needed in the cleanroom
P1.8Verification of the internal alignment of the instrumentDay4C1optical bench needed in the cleanroom
P1.9Science detector calibrationsDay1C1-
TotalContigency of 1 day 9+1=10

Phase 2 (Pre-commissioning)

SHARK-NIR Location : LBT platform (Some of the activities may run in parallel). All daytime activities.

NumberActivity NameDay / NightDuration (days)CategoryLBTO Support
P2.0Installation of the SHARK-NIR at LBT platformDay1 (preparation) + 1 (lift-off) + 1 (contigency)C1Crew members' support for the preparation, lift-off, and installation of SHARK-NIR, crane operator (mountain bay, LBT platform), safety officer, working platform installed infont of the gregorian focal-station SX, installation of electronics in LBTI/SHARK cabinet, check the installation document for more details
P2.1Activating the instrument and testing instrument states & transitionsDay1C2support to verify the working of emergency button/stop
P2.2Instrument operability and functioningDay0.5C2Liquid Nitrogen fill
P2.3TCS communication testDay0.5C2Authorise SHARK-NIR, connecting to ASM+LBTI AO system, able to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the fitswriter, support from LBT SW team
P2.4Align SHARK-NIR to the telescopeDay1+1C2working platform installed in front of the gregorian focal-station SX, Mounting RR on the SX side. Support on running SOUL AO
P2.5SOUL AO system testDay0.5C2working platform installed in front of the gregorian focal-station SX, Mounting RR on the SX side. Support on running SOUL AO
P2.6Measurement of NCPADay0.5C2 + C3Mounting RR on the SX side. Support on running SOUL AO
P2.7Looking for filter defects/effects/features+ Science detector calibrations repeatDay0.5C2Mounting RR on the SX side. Support on running SOUL AO
P2.8Flexure testsDay2.5C2 + C3Mounting RR on the SX side. Support on running SOUL AO, the telescope need to move in elevation
P2.9Cryostat warm up checkDay2C2-
TotalContigency included within 11 days Warming up time (of 2 days) not considered here

Phase 3 (Commissioning)

SHARK-NIR Location : LBT platform. Mostly nightime activities. Some daytime support (within SHARK-NIR) is anticipated.

NumberActivity NameDay / NightDuration (hours)CategoryLBTO Support
P3.18Large spatial scale instrument and telescope flat fieldTwilight2C5AO support
P3.1Telescope control – sending presetNight0.5C4AO support
P3.4Telescope control – telescope mode, offset, and focal plane geometry estimationNight1C4AO support
P3.31Pupil alignmentNight0.5C4AO support
P3.6Orient the coronagraphsNight1C4AO support
P3.32PSF AlignmentNight0.5C4AO support
P3.10Verify the ADC rotation on skyNight2C4AO support
P3.12Checking field-stabilized mode/bearing rotation serviceNight2C4AO support
P3.xxTT loop working and performance?Night2C4AO support
P3.xxNCPA working and performance (using the CU light source and star (Woll+DI-DBI))?Night6+6C4AO support
P3.5Check the acquisition procedureNight2C4AO support
P3.21Star center waffle imagesNight1C5AO support
P3.13Center the slitNight4C4AO support
P3.19Sky backgroundNight1C5AO support
P3.14Astrometry plate scale and orientationNight1C5AO support
P3.15Flux calibration (off-centered target observation)Night1C5AO support
P3.16Instrumental throughput and absolute flux calibrationNight1C5AO support
P3.17Atmospheric calibration and absolute flux calibrationNight1C5AO support
P3.29Distortion mapNight1C5AO support

Phase 4 (Science Verification / Early Science)

SHARK-NIR Location : LBT platform. Almost all nightime activities. Some daytime support (within SHARK-NIR) is anticipated.

NumberActivity NameDay / NightDuration (nights)CategoryLBTO Support
P4.1Direct imaging + field stabilized mode testing (95% cases)Night0.8C4 + C6AO support
P4.2Direct imaging + pupil stabilized mode testing (5% cases)Night0.2C4 + C6AO support
P4.3Coronagraphic imaging + field stabilization mode testingNight1C4 + C6AO support
P4.4Coronagraphic imaging + pupil stabilization mode testingNight1C4 + C6AO support
P4.5Long-slit spectrograph mode testingNight1C4 + C6AO support
P4.6xNight1C4 + C6AO support
P4.7Exo-planet: Giant planets and brown dwarfs in SFR, stellar associations, & young open clustersNight10C4 + C6AO support
P4.8Exo-planet: AstrometryNight4C4 + C6AO support
P4.9Exo-planet: Spectroscopic Characetization of known sub-stellar companionsNight5C4 + C6AO support
P4.10Disk: High-contrast images of circumstellar disksNight1C4 + C6AO support
P4.11Disk: Coronagraphic imaging of stellar jetsNight1C4 + C6AO support
P4.12Disk: Jets investigated with long-slit spectraNight1C4 + C6AO support
P4.13Extragalactic: QSO & AGNsNight4C4 + C6AO support
P4.14Solar system: Size and shape of main-belt astroidsNight1C4 + C6AO support
P4.15Solar system: Surface heterogeneity of trans-neptunian objectsNight1C4 + C6AO support
P4.16x?Night0.5C4 + C6AO support
P4.17x?Night0.5C4 + C6AO support

Note: The duration mentioned in Phase 4 will be changed to hours later.

Additional Information

To be added:

  1. Other performance activities, if any
  2. Look-up tables, if any

Comments

MDP

  • all operation that should be supported by control software automated procedures should be defined by the responsible person with software person in copy or in accordance with software department (better) (e.g.: P1.8 and P1.9)

Reminders

  • make sure if all the support from LBTI and iLOCATOR team are mentioned clearly (related to the installation of electronics in their cabinets, sharing space, access permissions, IP addresses, etc.)