wiki:docs/CommissioningPlan/P2.2

P2.2 Installation of SHARK-NIR and its electronics on the LBT platform

  • Phase : 2
  • Status : COMPLETE
  • Category : Installation of SHARK-NIR at LBT platform (C2)
  • Recurrence : once (unless deemed necessary to remove SHARK-NIR from the telescope platform)
  • Duration : 7 days (including 1 day contingency)

Description

  • Aligned SHARK-NIR is prepared for the Big-Lift and installed on the LBT platform.
  • Installation of the electronics in the cabinets, cabling, and confirming the safety & security of the instrument and area.

Prerequisites

  • SHARK-NIR is aligned and ready for the lift-off.
  • People required to access the electronics platform have completed the needed training
  • Equipment temporary connected to the rails interfering with installation removed (by LBTO personnel)

Procedure

  • Look at the AD3 document for the detailed procedure.
    • SHARK-NIR and its parts will be ready on the high bay. These components may be moved through the hatch to the telescope or moved by elevator to the telescope
      • shelves: use elevators
      • rails: use elevators
      • calendered structure: use elevators
      • shark-nir bench+ bearing on its red handling: lift up through the hatch.
      • camera on a cart with wheels (with a window on the bottom): lift up through the hatch or use elevators
    • Day 1
      • Shelves installation. (Pag. 70-89 of Installation Plan: SHARK-NIR-INAFP-MAN-001_Issue2.1) -Temporary installation of rails to identify interferences. Need to be disinstalled at end of the day, unless LBTO advises differently.
    • Day 2
      • 2 Rails installation. (Pag. 90-95 of Installation Plan: SHARK-NIR-INAFP-MAN-001_Issue2.1)
      • Installation of calendered structure on the shelves. (Pag. 95-111). At the end of the day calendered structure shall be secured to the shelves, otherwise it shall be removed, together with installation rails and procedure repeataed the next day.
    • Day 3
      • Install the SHARK-NIR optic bench on the calendered structure. (Pag. 111-141)
    • Day 4
      • Fix the cable chain. (Pag. 142-144)
      • Install patch boxes. (Pag. 144-145)
      • Fix cable from patch-boxes to instrument.
    • Day 5
      • Move the calendered structure at its final position. (Pag. 145-148)
      • SCICAM installation with MACIE already installed. (Pag. 148-163)
      • Installation of electronics and cabling from patch boxes to cabinets.
      • Prepare the deployable arm for its handling. (Pag. 164-171)
    • Day 6
      • Installation of the deployable arm. (Pag. 172-177)
      • Complete cabling.
      • Check movements of bearing, deployable arm, and shutter.
      • Cool down Cryostat.
      • Check the network connections and very basic functionalities after powering on.
    • Day 7
      • Contingency

Templates

Success criteria

  • SHARK-NIR is successfully installed on the LBT platform.
  • SHARK-NIR electronics are successfully installed.
  • Telescope is balanced.
  • Connect all the cables and secure them.
  • Reassure all the connections, nuts, bolts, etc.
  • Confirm the safety and security of the instrument and the area.

Notes

  • Activities on High-bay and telescope.
  • Note that SHARK-NIR is NOT installed as a single piece. The cryostat has to be disassembled from the bearing before the installation can start. Please look into the AD3 document for details.
  • Note that othe Lakeshore of the SHARK-NIR electronics is installed within the LBTI electronics cabinets, the rest of the electronics is in the cabinet shared with iLocater.
  • check this link (https://docs.google.com/document/d/1r0SDiy9yBEfGQjDI6hCXT9hfRDRJ4dh4nNUZ3JHClJE/edit) for some details on the alignment day to day plan.
  • Considering October timelines, as per LBTO information. Platform installation can start at 08:00 and takes about 40 minutes. 2 people can handle it. Platform use stops at 16:00, and dismounting takes about 30 mins.
  • No extra crew is needed on the telescope during weekends for the platform, as the operation can be handled by personnel already available at the telescope.

LBTO support

  • Crew members' support for the preparation, lift-off, and installation of SHARK-NIR and its electronics
  • Crane operator (cleanroom, mountain bay, LBT platform)
  • Safety officer
  • Working platform installed in front of the Gregorian focal-station SX
  • Hatch door SX on the UIAP platform removed
  • Support for the installation of electronics in the LBTO cabinet
  • Liquid nitrogen fill
  • Vacuum pump to pump down cryostat (See activity P1.4 and P1.5 for more details)
  • Kindly check the installation document, AD3, for more details

Date performed and by whom

Notes