P1.6 SCICAM refocussing

  • Phase : 1
  • Status : COMPLETE
  • Category : Unpack, Assemble, and Verification (C1)
  • Recurrence : once
  • Duration : 1.5 day

Description

  • The SCICAM of the SHARK-NIR is believed to be not in-focus position. The detector team at Steward Observatory will have the cryostat at an early stage (prior to SHARK-NIR arriving at LBT) to look into several aspects including the focussing issue. Depending on the outcome of this intervention, refocussing of the cryostat is anticipated.

Prerequisites

  • SHARK-NIR is connected to the LBT network.
  • Electronics cabinets on.
  • Steward Observatory Detector Team has completed the work and the information is passed on to the SHARK-NIR team.
  • Cryostat cooled down.

Procedure

  • Mount the cryostat to the SHARK-NIR optical bench.
  • Use several shims one after the other to take images at the detector.
  • Using the through-focus images, find the right shim to have the detector at the focus position.
  • Make the shim of the right dimensions.
  • Use this shim, and mount the cryostat to the SHARK-NIR optical bench.
  • Verify that the final configuration produces focused images.

Templates

Success criteria

  • SCICAM is focused.

Notes

LBTO support

  • Support to use of the workshop at LBT.

Date performed and by whom

Last modified 22 months ago Last modified on 08/13/22 07:55:48