wiki:docs/CommissioningPlan/P1.8

P1.8 Complete system functional verification, filter artifacts/defects verification, NCPA measurement, and internal tip-tilt loop verification

  • Phase : 1
  • Status : COMPLETE
  • Category : Unpack, Assemble, and Verification (C1)
  • Recurrence : once
  • Duration : 1.5 days

Description

  • Checking the working of motors and light sources within SHARK-NIR using optical feedback. Finding the filter defects/artifacts using an internal calibration source (flat-field) within the instrument. Measure the NCPA internal to the SHARK-NIR and correct using the ALPAO-DM. Check the working of the internal tip-tilt loop using calibration unit light sources, C-RED2, and ALPAO-DM.

Prerequisites

  • SHARK-NIR is connected to the LBT network.
  • Electronics racks on.
  • DM best shape uploaded (shape minimizing internal aberrations)
  • The cryostat should be running and cooled down.
  • P1.7 should be completed.

Procedure

  • When the services are up and running, after the motors are sent to home positions, each of the individual motors is individually tested for their different named/nominal positions.
  • The light sources within SHARK-NIR are used simultaneously to check the working of the motors by looking at the optical feedback.
  • Check the CRED-2 and ALPAO-DM SW using optical feedback.
  • Take the images of all the filters using the internal calibration source (flat-field) within the instrument to locate/find out the filter defects/artifacts, if any. You may take short- and long exposures to get better contrast of the features if required.
  • Check the filter wheel position monitoring script detailed in SNM1. Save the data in the repository.
  • Run the Phase-diversity routine using the images taken with the SHARK-NIR internal calibration sources to measure the NCPA within (excluding the deployable arm).
  • Run the internal tip-tilt loop routine for a defined (or set of) brightness of the source (star).
  • Check its efficiency in keeping the PSF at the C-RED2 hot-pixel.
  • Save data to the repository and analyze them.

Templates

  • SHARKNIR_di_mon_MaskRepeatability
  • SHARKNIR_di_cal_NCPA_PD (Phase Diversity approach)
  • SHARKNIR_di_cal_NCPA_trial (Trial & Error approach)
  • SHARKNIR_gen_tec_CloseLoop
  • SHARKNIR_gen_tec_OpenLoop

Success criteria

  • All the motors can reach the named positions / nominal positions.
  • All the light sources are working and confirmed through optical feedback at the SCICAM.
  • Filter wheel position monitoring script is run successfully and data is saved in the repository.
  • CRED-2 AND ALPAO-DM working normally.
  • All the filter images are saved.
  • Internal NCPA is measured and the PSF shows improvement in its quality after the NCPA correction using the ALPAO DM.
  • Internal tip-tilt routine works fine and the PSF at the C-RED2 is stable within the required precision.
  • All the data and analysis are saved in the repository
  • Completed. The data can be found in this link.

Notes

LBTO support

  • Liquid Nitrogen refill is required in the cleanroom.

Date performed and by whom Elena, Luca

Last modified 7 months ago Last modified on 10/12/23 10:45:55