wiki:docs/CommissioningPlan/P2.0

P2.0 SHARK-NIR Open Cart Activities

  • Phase : 2
  • Status : COMPLETE
  • Category : Unpack, Assemble, Verification, and Installation (C1)
  • Recurrence : once (unless deemed necessary to remove SHARK-NIR from the telescope platform)
  • Duration : 1 day

Description

  • All activities are to be done on the SHARK-NIR optical bench with the cart open.

Prerequisites

  • electronics lab cleaned up by LBTO

Procedure

  • For each rotatory stage, PI116.DGH:
    • put two drops of Rodorsil 47V500 oil on the shaft of the filter wheels without dismounting anything. Make the mirror rotate a few times completely so that the oil distributes on the whole shaft.
    • leave the C-RED2 ND filter wheel as last since it requires dismounting the folding mirror and the lens.
  • Re-align both SCI filter wheels tilt to eliminate ghosts from flat field images.
  • Install barometric pressure gauge (details to be added)
  • clean the optical bench

Success criteria

  • All activities successfully completed and tested the proper functioning,

Notes

  • Activity in the LBT Electronic room.

LBTO support

Associated SHARK-NIR personnel

Date performed and by whom Minimum number of people available from SN team: 2+1 SW. Comments Luca to provide detail on oil and method to be used, if needed.

Last modified 19 months ago Last modified on 10/28/22 18:22:11