P2.8 Science detector calibrations and total check up
- Phase : 2
- Status : Draft
- Category : Daytime testing (functionality and operability) (C2)
- Recurrence : once at commissioning
- Duration : 1 day
Description
- After the installation of the SHARK-NIR at the LBT platform, the science detector is tested for all its read-out modes, windowing possibilities. Also, some of the calibration scripts are rechecked.
Prerequisites
- SCICAM cooled down.
Procedure
- Repeat the science calibrations below (some of these are performed when SHARK-NIR was in the LBT cleanroom. Check P1.11) for details.
Success criteria
- All calibrations successfully tested.
- All the read-out modes and windowing possibilities of the SCICAM are tested successfully.
- All relevant information (files) are saved in the repository.
Notes
- The time dedicated to this activity has to be considered in combination with other activities. Parallelism is possible.