wiki:docs/CommissioningPlan/SDC1

SDC1 Instrumental background for science

  • Phase : 1
  • Status : COMPLETE
  • Category : Daytime calibration (C3)
  • Recurrence : every day starting from commissioning.
  • Duration : 20 minutes (this duration is valid only during regular operations, i.e., after commissioning)

Description

  • Take instrumental background for the same night setup with closed dome and instrument. Note that there are no lights for this testing. The purpose is to remove the instrumental background from science images.

Prerequisites

Procedure

  • Observe the instrumental background in the same setup of the night with all lights off and dome and instrument (shutter) closed.

Templates

  • SHARKNIR_cal_InstrumentBackground

Success criteria

  • Accuracy is better than 10%.

Notes

  • Same as activity 7.7 in AD4

LBTO support

Date performed and by whom

Last modified 15 months ago Last modified on 10/12/23 11:13:11