P2.8 Science detector calibrations and total check up

  • Phase : 2
  • Status : Draft
  • Category : Daytime testing (functionality and operability) (C3) + Daytime calibration (C4)
  • Recurrence : once at commissioning
  • Duration : 1 day

Description

  • After the installation of the SHARK-NIR at the LBT platform, the science detector is tested for all its read-out modes, windowing possibilities. Also, some of the calibration scripts are rechecked.

Prerequisites

  • SCICAM cooled down.

Procedure

  • Repeat the science calibrations below (some of these are performed when SHARK-NIR was in the LBT cleanroom or at Padova cleanroom. Check P1.11) for details.
CodeActivityLocation to perform this test
SDC1Instrumental background for sciencePadova / LBT cleanroom / LBT Platform
SDC2Instrument flat field, detector linearity and bad pixelsPadova / LBT cleanroom / LBT Platform
SDC3Wavelength calibrationPadova / LBT cleanroom / LBT Platform
SDC4Thermal backgroundPadova / LBT cleanroom / LBT Platform
SDC5Detector gainPadova / LBT cleanroom / LBT Platform
SDC6Detector persistencePadova / LBT cleanroom / LBT Platform
SDC7Spectral resolutionPadova / LBT cleanroom / LBT Platform
SDC8Ghost calibrationPadova / LBT cleanroom / LBT Platform

Success criteria

  • All calibrations successfully tested.
  • All relevant information (files) are saved in the repository.

Notes

  • The time dedicated to this activity has to be considered in combination with other activities. Parallelism is possible.