Version 5 (modified by kradhakrishnan, 4 years ago) (diff) |
---|
P1.9 Science detector calibrations
- Phase : 1
- Status : Draft
- Category : Unpack, Assemble, Verification, and Installation (C1)
- Recurrence : once
- Duration : 1 day
Description
- Calibration and testing of the SHARK-NIR science detector
Prerequisites
- SHARK-NIR connected to LBT network.
- Electronics cabinets on.
- The cryostat should be running and cooled down.
- Internal alignment of the SHARK-NIR is verified.
Procedure
- check linearity, create bad pixel mask, bias calibration, master dark, and then perform the following daytime calibration procedures below.
Success criteria
- linearity as expected
- bad pixels mask created
- bias and flat took
- All individual activity (in the table) success criteria is met
Notes
- Save all the intermediate images to check the SHARK-NIR Data Reduction pipeline.
LBTO support
Associated SHARK-NIR personnel
Date performed and by whom