P1.11 Science detector calibrations
- Phase : 1
- Status : Draft
- Category : Unpack, Assemble, and Verification (C1) + Daytime calibration (C4)
- Recurrence : starting from commissioining. daily/weekly/monthly/yearly depending on individual activities.
- Duration : 1 day
Description
- Calibration and testing of the SHARK-NIR science detector
Prerequisites
- SHARK-NIR connected to LBT network.
- Electronics cabinets on.
- The cryostat should be running and cooled down.
- Internal alignment of the SHARK-NIR is verified.
Procedure
- Check bias calibration & master dark scripts and then perform the following daytime calibration procedures below.
Code | Activity | Location to perform this test |
SDC1 | Instrumental background for science | Padova / LBT cleanroom / LBT Platform |
SDC2 | Instrument flat field, detector linearity and bad pixels | Padova / LBT cleanroom |
SDC3 | Wavelength calibration | Padova / LBT cleanroom? |
SDC4 | Thermal background | Padova / LBT cleanroom / LBT Platform |
SDC5 | Detector gain | Padova / LBT cleanroom / LBT Platform? |
SDC6 | Detector persistence | Padova / LBT cleanroom / LBT Platform? |
SDC7 | Spectral resolution | Padova / LBT cleanroom |
SDC8 | Ghost calibration | Padova |
- Check the working of all the detector read-out modes and windowing possibilities. Note that this will be checked rigorously in the Padova laboratory.
Templates
Success criteria
- linearity as expected
- bad pixels mask created
- bias and flat took
- All individual activity (in the table) success criteria are met.
Notes
- Save all the intermediate images to check the SHARK-NIR Data Reduction pipeline.
LBTO support
- Liquid Nitrogen refill is required in the cleanroom.
Date performed and by whom