Version 6 (modified by kradhakrishnan, 4 years ago) (diff) |
---|
P1.11 Science detector calibrations
- Phase : 1
- Status : Draft
- Category : Unpack, Assemble, and Verification (C1) + Daytime calibration (C4)
- Recurrence : starting from commissioining. daily/weekly/monthly/yearly depending on individual activites.
- Duration : 1 day
Description
- Calibration and testing of the SHARK-NIR science detector
Prerequisites
- SHARK-NIR connected to LBT network.
- Electronics cabinets on.
- The cryostat should be running and cooled down.
- Internal alignment of the SHARK-NIR is verified.
Procedure
- Check bias calibration & master dark scripts and then perform the following daytime calibration procedures below.
- Check the working of all the detector read-out modes and windowing possibilities.
Success criteria
- linearity as expected
- bad pixels mask created
- bias and flat took
- All individual activity (in the table) success criteria is met
Notes
- Save all the intermediate images to check the SHARK-NIR Data Reduction pipeline.
LBTO support
- Liquid Nitrogen refill is required in the cleanroom.
Associated SHARK-NIR personnel
Date performed and by whom
Comments