P1.11 Science detector calibrations
- Phase : 1
- Status : Draft
- Category : Daytime testing (functionality and operability) (C3) + Daytime calibration (C4)
- Recurrence : starting from commissioining. daily/weekly/monthly/yearly depending on individual activities.
- Duration : 1 day
Description
- Calibration and testing of the SHARK-NIR science detector.
Prerequisites
- SHARK-NIR connected to LBT network.
- Electronics cabinets on.
- The cryostat should be running and cooled down.
- Internal alignment of the SHARK-NIR is verified.
Procedure
- Check bias calibration & master dark scripts and then perform the following daytime calibration procedures below.
Code | Activity | Location to perform this test |
SDC1 | Instrumental background for science | Padova / LBT cleanroom / LBT Platform |
SDC2 | Instrument flat field, detector linearity and bad pixels | Padova / LBT cleanroom |
SDC3 | Wavelength calibration | Padova / LBT cleanroom |
SDC4 | Thermal background | Padova / LBT cleanroom / LBT Platform |
SDC5 | Detector gain | Padova / LBT cleanroom / LBT Platform |
SDC6 | Detector persistence | Padova / LBT cleanroom / LBT Platform |
SDC7 | Spectral resolution | Padova / LBT cleanroom |
SDC8 | Ghost calibration | Padova |
- Check the working of all the detector read-out modes and windowing possibilities. Note that this will be checked rigorously in the Padova laboratory.
Templates
- SHARKNIR_cal_InstrumentBackground (not released)
- SHARKNIR_gen_cal_InstrumentFlatField (not released)
- SHARKNIR_lss_cal_Wavelenght (not released)
- SHARKNIR_gen_mon_ThermalBackground (not released)
- SHARKNIR_di_mon_DetectorGain (not released)
- SHARKNIR_ci_mon_DetectorPersistence (not released)
- SHARKNIR_lss_mon_SpectraResolution (not released)
- SHARKNIR_cal_mon_Ghost (not released)
Success criteria
- SCICAM linearity as expected.
- SCICAM bad pixels mask created.
- SCICAM bias and flat scripts working.
- All individual activity (in the table) success criteria are met.
Notes
- Save all the intermediate images to check the SHARK-NIR Data Reduction pipeline.
LBTO support
- Liquid Nitrogen refill is required in the cleanroom.
Date performed and by whom