P2.0 Installation of SHARK-NIR at the LBT platform
- Phase : 2
- Status : Draft
- Category : Unpack, Assemble, Verification, and Installation (C1)
- Recurrence : once
- Duration : 2 days for preparation, 1 day for installation , and 1 day contingency.
Description
- Aligned SHARK-NIR is prepared for the Big-Lift and installed on the LBT platform.
Prerequisites
- SHARK-NIR is aligned and ready for the lift-off.
Procedure
- Look at this document for the procedure and details.
Success criteria
- SHARK-NIR successfully installed at the LBT platform.
- Telescope is balanced.
- Connect all the cables and secure them.
- Reassure all the connections, nuts and bolts, etc.
Notes
LBTO support
- Crew members' support for the preparation, lift-off, and installation of SHARK-NIR
- Crane operator (mountain bay, LBT platform)
- Safety officer
- Working platform installed in front of the Gregorian focal-station SX,
- Support for the installation of electronics in LBTI/SHARK cabinet
- kindly check the installation document for more details
Associated SHARK-NIR personnel
Date performed and by whom
Comments
MB: Please specify that Cryostat has to be diassembled from bearing before the installation can start. Put AD number instead of link. Concerning recurrence, in principle is only one, however optical bench only might have very low chances of being dismounted at some point for refurbishment of components which might be hard to happen in place