wiki:docs/CommissioningPlan/P2.0

Version 5 (modified by kradhakrishnan, 4 years ago) (diff)

--

P2.0 Installation of SHARK-NIR at the LBT platform

  • Phase : 2
  • Status : Draft
  • Category : Unpack, Assemble, Verification, and Installation (C1)
  • Recurrence : once
  • Duration : 2 days for preparation, 1 day for installation , and 1 day contingency.

Description

  • Aligned SHARK-NIR is prepared for the Big-Lift and installed on the LBT platform.

Prerequisites

  • SHARK-NIR is aligned and ready for the lift-off.

Procedure

  • Look at this document for the procedure and details.

Success criteria

  • SHARK-NIR successfully installed at the LBT platform.
  • Telescope is balanced.
  • Connect all the cables and secure them.
  • Reassure all the connections, nuts and bolts, etc.

Notes

LBTO support

  • Crew members' support for the preparation, lift-off, and installation of SHARK-NIR
  • Crane operator (mountain bay, LBT platform)
  • Safety officer
  • Working platform installed in front of the Gregorian focal-station SX,
  • Support for the installation of electronics in LBTI/SHARK cabinet
  • kindly check the installation document for more details

Associated SHARK-NIR personnel

Date performed and by whom