wiki:docs/CommissioningPlan/P1.7

Version 17 (modified by kradhakrishnan, 3 years ago) (diff)

--

P1.7 Science detector calibrations

  • Phase : 1
  • Status : Draft
  • Category : Daytime testing (functionality and operability) (C3) + Daytime calibration (C4)
  • Recurrence : starting from commissioining. daily/weekly/monthly/yearly depending on individual activities.
  • Duration : 0.5 day

Description

  • Calibration and testing of the SHARK-NIR science detector.

Prerequisites

  • SHARK-NIR connected to LBT network.
  • Electronics cabinets on.
  • The cryostat should be running and cooled down.
  • Internal alignment of the SHARK-NIR is verified.

Procedure

  • Check bias calibration & master dark scripts and then perform the following daytime calibration procedures below.
CodeActivityLocation to perform this test
SDC1Instrumental background for sciencePadova / LBT cleanroom / LBT Platform
SDC2Instrument flat field, detector linearity and bad pixelsPadova / LBT cleanroom
SDC3Wavelength calibrationPadova / LBT cleanroom
SDC4Thermal backgroundPadova / LBT cleanroom / LBT Platform
SDC5Detector gainPadova / LBT cleanroom / LBT Platform
SDC6Detector persistencePadova / LBT cleanroom / LBT Platform
SDC7Spectral resolutionPadova / LBT cleanroom
SDC8Ghost calibrationPadova
  • Check the working of all the detector read-out modes and windowing possibilities. Note that this will be checked rigorously in the Padova laboratory.

Templates

  • SHARKNIR_cal_InstrumentBackground (not released)
  • SHARKNIR_gen_cal_InstrumentFlatField (not released)
  • SHARKNIR_lss_cal_Wavelenght (not released)
  • SHARKNIR_gen_mon_ThermalBackground (not released)
  • SHARKNIR_di_mon_DetectorGain (not released)
  • SHARKNIR_ci_mon_DetectorPersistence (not released)
  • SHARKNIR_lss_mon_SpectraResolution (not released)
  • SHARKNIR_cal_mon_Ghost (not released)

Success criteria

  • SCICAM linearity as expected.
  • SCICAM bad pixels mask created.
  • SCICAM bias and flat scripts working.
  • All individual activity (in the table) success criteria are met.

Notes

  • Save all the intermediate images to check the SHARK-NIR Data Reduction pipeline.

LBTO support

  • Liquid Nitrogen refill is required in the cleanroom.

Date performed and by whom