Changes between Version 3 and Version 4 of docs/CommissioningPlan/P3.9


Ignore:
Timestamp:
02/04/21 22:47:14 (4 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P3.9

    v3 v4  
    22•       **Phase**               :       3 
    33•       **Status**              :       Draft   
    4 •       **Category**            :       Nighttime testing (functionality and operability) (C4)
     4•       **Category**            :       Nighttime testing (functionality and operability) (C5) + Nighttime testing for performance (C7)
    55•       **Recurrence**  :       once at commissioning
    6 •       **Duration**            :       2 hours
     6•       **Duration**            :       2 nights
    77**Description**
    88•       Evaluate the performance of the internal tip-tilt (TT) loop of SHARK-NIR for stars of varying brightness.
    99**Prerequisites**
    10 •       Atmospheric conditions: ?
     10•       Atmospheric conditions: TBD
    1111•       Authorize SHARK-NIR on the SX side.
    1212•      Stars (of known brightness from 8mag-13mag in R band) as targets.
     
    1818* Use data to estimate the improvement of the residual jitter after the TT loop is closed.
    1919* Repeat for different star magnitudes.
    20 * should we perform as a function of elevation as well? we can chose stars accordingly then?
     20* should we perform as a function of elevation as well? we can choose stars accordingly then?
    2121
    2222**Success criteria**