Version 3 (modified by kradhakrishnan, 4 years ago) (diff) |
---|
P3.9 Internal TT loop working and performance
- Phase : 3
- Status : Draft
- Category : Nighttime testing (functionality and operability) (C4)
- Recurrence : once at commissioning
- Duration : 2 hours
Description
- Evaluate the performance of the internal tip-tilt (TT) loop of SHARK-NIR for stars of varying brightness.
Prerequisites
- Atmospheric conditions: ?
- Authorize SHARK-NIR on the SX side.
- Stars (of known brightness from 8mag-13mag in R band) as targets.
- AO working.
Procedure
- Run the internal TT loop after the star is acquired and the AO loop is closed.
- Take unsaturated images of the star for a given (?) science filter before and after the internal TT loop closure in the SCICAM.
- Take data in TECCAM simultaneously.
- Use data to estimate the improvement of the residual jitter after the TT loop is closed.
- Repeat for different star magnitudes.
- should we perform as a function of elevation as well? we can chose stars accordingly then?
Success criteria
- Estimate the residual jitter after SOUL-AO is closed for a given seeing and star brightness.
- Checking the working and performance of the internal TT loop.
- Quantify and numbers to add?
Notes
LBTO support
- SOUL-AO support
Associated SHARK-NIR personnel
Date performed and by whom