wiki:docs/CommissioningPlan/P3.9

P3.9 Check the acquisition procedure

  • Phase : 3
  • Status : COMPLETE
  • Category : Nighttime testing (functionality and operability) (C5)
  • Recurrence : once at commissioning
  • Duration : 2 hours

Description

  • Verify the acquisition sequence for SHARK-NIR

Prerequisites

  • Atmospheric conditions: should be able to see bright stars in the sky (preferably close to zenith?).
  • Authorize SHARK-NIR on the SX side.
  • Suitable bright enough target (including the possibility of performing AO).

Procedure

  • Start the acquisition sequence: collimating the telescope to reduce the aberrations, close the loop and produce better ASM flat, NCPA estimation using phase-diversity algorithm, close SHARK-NIR tip-tilt+NCPA loop, and check the PSF quality at SCICAM.
  • Save telemetry (open and closed loop of the ALPAO DM).

Templates

  • SHARKNIR_di_acq - direct imaging mode (not released)
  • SHARKNIR_di_obs - direct imaging mode
  • SHARKNIR_ci_acq - coronagraphic mode (not released)
  • SHARKNIR_ci_obs - coronagraphic mode
  • SHARKNIR_lss_acq - long slit spectroscopy mode (not released)
  • SHARKNIR_lss_obs - long slit spectroscopy mode

Success criteria

  • Successful acquisition sequence.

Notes

LBTO support

  • AO support

Date performed and by whom

Last modified 7 months ago Last modified on 10/12/23 17:17:06