     1== P3.5 Check the acquisition **Procedure** ==
     2•       **Phase**               :       3 
     3•       **Status**              :       Draft   
     4•       **Category**            :       Nighttime testing (functionality and operability) (C4)
     5•       **Recurrence**  :       once at commissioning
     6•       **Duration**            :       1 hour(s)
     7**Description**
     8•       Verify the acquisition sequence for SHARK-NIR
     9**Prerequisites**
     10•       Atmospheric conditions: should be able to see bight stars on sky (preferably close to zenith?).
     11•       Authorize SHARK-NIR on the SX side.
     12•       Suitable bright enough target (including the possibility of performing AO).
     13**Procedure**
     14•       Start the acquisition sequence: collimating the telescope to reduce the aberrations, close the loop and produce better ASM flat, NCPA estimation using phase-diversity algorithm, close SHARK-NIR tip-tilt+NCPA loop, and check the PSF quality at SCICAM.
     15•       Save telemetry (open and closed loop of the ALPAO DM).
     16**Success criteria**
     17•       Successful acquisition sequence.
     18**Notes**
     19**LBTO support**
     20•       Support from LBTI/LBTO?
     21•       Presence of John Hill usually helps while collimating for first time.
     22•       Steve Allenson (as the TO) will be a great asset too.
     23**Associated SHARK-NIR personnel**
     24•       JF, LM, MdP, MM (from AZ), DV?
     25**Date performed and by whom**