P3.3 SOUL-AO verification

  • Phase : 3
  • Status : Draft
  • Category : Nighttime testing (functionality and operability) (C5) + Nighttime testing for performance (C7)
  • Recurrence : after instrument installation at telescope platform
  • Duration : 1 night

Description

  • Proper working and tuning of the SOUL-AO parameters are verified. If minor adjustments are required, they are either implemented immediately or marked for later daytime work. Also, the SOUL AO performance is verified for various stars of different magnitudes.

Prerequisites

  • Activities P1.12 and P2.5 are successfully completed.

Procedure

  • AO verification procedure TBD
  • AO performance procedure TBD

Templates

Success criteria

  • SOUL AO system is working in tandem with the SHARK-NIR system.
  • Acceptable improvement of the on-axis PSF for a given seeing and brightness of the star.

Notes

LBTO support

  • AO Support

Date performed and by whom