wiki:docs/CommissioningPlan/P1.12

P1.12 Verification of the contrast for coronagraphic masks

  • Phase : 1
  • Status : COMPLETE
  • Category : Daytime testing (functionality and operability) (C3)
  • Recurrence : once
  • Duration : 1 day

Description

  • Verify the center mask algorithm, and calculate the rejection factor. Verify the contrast obtained for different sets of masks on the scientific camera.

Prerequisites

  • SHARK-NIR is connected to the LBT network.
  • Electronics cabinets on.
  • The cryostat should be running and cooled down.
  • Activity P1.0 (and, if required, P1.11) should be completed.

Procedure

  • TBW

Templates

  • SHARKNIR_gen_tec_PSFAlignment
  • SHARKNIR_gen_tec_PupilApoAlignment
  • SHARKNIR_gen_tec_PupilLyotAlignment

Success criteria

  • The mask-centering algorithm works efficiently.
  • The raw contrast estimated is within specifications for all the coronagraphic masks.

Notes

LBTO support

  • Liquid Nitrogen refill is required in the cleanroom.

Date performed and by whom

Last modified 7 months ago Last modified on 10/12/23 10:47:13