    11== P3.3 SOUL-AO verification ==
    2 •       **Phase**               :       3 
    3 •       **Status**              :       Draft   
    4 •       **Category**            :       Nighttime testing (functionality and operability) (C5) + Nighttime testing for performance (C7)
    5 •       **Recurrence**  :       after instrument installation at telescope platform
    6 •       **Duration**            :       1 night
     2
     3- **Phase**             :       3 
     4- **Status**            :       Draft   
     5- **Category**  :       Nighttime testing (functionality and operability) (C5) + Nighttime testing for performance (C7)
     6- **Recurrence**        :       after instrument installation at telescope platform
     7- **Duration**  :       1 night
     8
    79**Description**
    8 •       Proper working and tuning of the SOUL-AO parameters are verified. If any minor adjustments are required, they are either implemented immediately or marked for later daytime work. Also for various stars of different magnitudes, the SOUL AO performance is verified.
     10- Proper working and tuning of the SOUL-AO parameters are verified. If minor adjustments are required, they are either implemented immediately or marked for later daytime work. Also, the SOUL AO performance is verified for various stars of different magnitudes.
    911
    1012**Prerequisites**
    11 
    12 * Activities [wiki:/docs/CommissioningPlan/P1.12 P1.12] and [wiki:/docs/CommissioningPlan/P2.5 P2.5] are successfully completed.
    13 
     13- Activities [wiki:/docs/CommissioningPlan/P1.12 P1.12] and [wiki:/docs/CommissioningPlan/P2.5 P2.5] are successfully completed.
    1414
    1515**Procedure**
    16 •       AO verification procedure TBD
    17 * AO performance procedure TBS
     16- AO verification procedure TBD
     17- AO performance procedure TBD
     18
     19**Templates**
    1820
    1921**Success criteria**
    20 •       SOUL AO system working in tandem with the SHARK-NIR system.
    21 •       Acceptable improvement of the on-axis PSF for a given seeing and brightness of the star.
     22- SOUL AO system is working in tandem with the SHARK-NIR system.
     23- Acceptable improvement of the on-axis PSF for a given seeing and brightness of the star.
    2224
    2325**Notes**
    2426
    2527**LBTO support**
    26 * AO Support
    27 
    28 **Associated SHARK-NIR personnel**
    29 
     28- AO Support
    3029
    3130**Date performed and by whom**