    1  == P3.7        Verify the ADC rotation on sky ==
     1 == P3.10       NCPA working and performance ==
    22•       **Phase**               :       3 
    33•       **Status**              :       Draft   
    44•       **Category**            :       Nighttime testing (functionality and operability) (C4)
    55•       **Recurrence**  :       once at commissioning
    6 •       **Duration**            :       4 hours
     6•       **Duration**            :       12 hours
    77**Description**
    8 •       Evaluate
     8•       Evaluate the NCPA working and performance using the baseline approach, phase-diversity approach, combination of both, and measurement of NCPA using the Wollaston prison & dual-band imaging.
     9
    910**Prerequisites**
    10 •       Atmospheric conditions: photometric.
     11•       Atmospheric conditions: ?
    1112•       Authorize SHARK-NIR on the SX side.
    12 •       Photometric stars as targets for every filter.
    1313•       AO working.
    14 •       Target(s) at different Zenith distances?
     14•       Target(s) at different Zenith distances with different magnitudes?
     15
    1516**Procedure**
    16 •       Check the working of the ADC using different targets in varying zenith distances and observing using different science filters?
     17•       Acquire star of given magnitude. Start SOUL-AO.
     18* Check the working and performance of the NCPA baseline approach. Take images at SCICAM.
     19* Check the phase diversity approach (using the internal calibration source). Take images at SCICAM.
     20* Check the phase diversity approach using Wollaston prism + DI-DBI. Take images at SCICAM.
     21* Repeat for a different star (of different magnitudes and for different elevation of the telescope)
     22
    1723**Success criteria**
    18 •       xxx
     24•       ???
    1925**Notes**
    2026
    2127**LBTO support**
    2228•       SOUL-AO support
     29
    2330**Associated SHARK-NIR personnel**