wiki:docs/CommissioningPlan/P3.10

Version 3 (modified by kradhakrishnan, 4 years ago) (diff)

--

P3.10 NCPA working and performance

  • Phase : 3
  • Status : Draft
  • Category : Nighttime testing (functionality and operability) (C4)
  • Recurrence : once at commissioning
  • Duration : 12 hours

Description

  • Evaluate the NCPA working and performance using the baseline approach, phase-diversity approach, combination of both, and measurement of NCPA using the Wollaston prison & dual-band imaging.

Prerequisites

  • Atmospheric conditions: ?
  • Authorize SHARK-NIR on the SX side.
  • AO working.
  • Target(s) at different Zenith distances with different magnitudes?

Procedure

  • Acquire star of given magnitude. Start SOUL-AO.
  • Check the working and performance of the NCPA baseline approach. Take images at SCICAM.
  • Check the phase diversity approach (using the internal calibration source). Take images at SCICAM.
  • Check the phase diversity approach using Wollaston prism + DI-DBI. Take images at SCICAM.
  • Repeat for a different star (of different magnitudes and for different elevation of the telescope)

Success criteria

  • ???

Notes

LBTO support

  • SOUL-AO support

Associated SHARK-NIR personnel

Date performed and by whom