    1 == P2.9 Cryostat warm up check  ==
    2 •       **Phase**               :       1 
    3 •       **Status**              :       Draft   
    4 •       **Category**            :       Daytime testing (functionality and operability) (C3)
    5 •       **Recurrence**  :       at the end of every SHARK-NIR run?
    6 •       **Duration**            :       2 days
     1== P2.9 Science detector calibrations (on the telescope)==
     2
     3- **Phase**             :       2 
     4- **Status**            :       Draft   
     5- **Category**  :       Daytime testing (functionality and operability) (C3) + Daytime calibration (C4)
     6- **Recurrence**        :       on a regular basis as per the requirement
     7- **Duration**  :       1 day
     8
    79**Description**
    8 •       Checking the cryostat warming up procedure.
     10- After installing the SHARK-NIR at the LBT platform, the science detector is tested for all its read-out modes, windowing possibilities. Also, some of the calibration scripts are rechecked.
     11
    912**Prerequisites**
    10 •       SHARK-NIR connected to LBT network.
    11 •       Automatic logging of the cryostat temperature
     13- SCICAM cooled down.
     14
    1215**Procedure**
    13 •       Run the cryostat warm up sequence
    14 •       Check how the system is performing every 30 minutes
     16- Repeat the science calibrations below (some of these are performed when SHARK-NIR was in the LBT cleanroom or at Padova cleanroom. Check [wiki:/docs/CommissioningPlan/P1.11 P1.11]) for details.
     17||**Code**||**Activity**||**Location to perform this test**||
     18||SDC1||[wiki:/docs/CommissioningPlan/SDC1 Instrumental background for science]||Padova / LBT cleanroom / LBT Platform||
     19||SDC2||[wiki:/docs/CommissioningPlan/SDC2 Instrument flat field, detector linearity and bad pixels]||Padova / LBT cleanroom||
     20||SDC3||[wiki:/docs/CommissioningPlan/SDC3 Wavelength calibration]||Padova / LBT cleanroom?||
     21||SDC4||[wiki:/docs/CommissioningPlan/SDC4 Thermal background]||Padova / LBT cleanroom / LBT Platform||
     22||SDC5||[wiki:/docs/CommissioningPlan/SDC5 Detector gain]||Padova / LBT cleanroom / LBT Platform?||
     23||SDC6||[wiki:/docs/CommissioningPlan/SDC6 Detector persistence]||Padova / LBT cleanroom / LBT Platform?||
     24||SDC7||[wiki:/docs/CommissioningPlan/SDC7 Spectral resolution]||Padova / LBT cleanroom||
     25||SDC8||[wiki:/docs/CommissioningPlan/SDC8 Ghost calibration]||Padova||
     26
     27**Templates**
     28
    1529**Success criteria**
    16 •       Cryostat warmed up without any issues.
    17 •       The temperature at the detector is stable at dome temperature.
     30- All calibrations are successfully tested.
     31- All relevant information (files) are saved in the repository.
     32
    1833**Notes**
     34- The time dedicated to this activity has to be considered in combination with other activities. Parallelism is possible.
    1935
    2036**LBTO support**
    2137
    22 **Associated SHARK-NIR personnel**
    23 
    2438**Date performed and by whom**