Changes between Version 10 and Version 11 of docs/CommissioningPlan/P2.9
- Timestamp:
- 01/14/22 18:00:47 (3 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P2.9
v10 v11 1 == P2.9 Cryostat warm up check == 2 • **Phase** : 1 3 • **Status** : Draft 4 • **Category** : Daytime testing (functionality and operability) (C3) 5 • **Recurrence** : at the end of every SHARK-NIR run? 6 • **Duration** : 2 days 1 == P2.9 Science detector calibrations (on the telescope)== 2 3 - **Phase** : 2 4 - **Status** : Draft 5 - **Category** : Daytime testing (functionality and operability) (C3) + Daytime calibration (C4) 6 - **Recurrence** : on a regular basis as per the requirement 7 - **Duration** : 1 day 8 7 9 **Description** 8 • Checking the cryostat warming up procedure. 10 - After installing the SHARK-NIR at the LBT platform, the science detector is tested for all its read-out modes, windowing possibilities. Also, some of the calibration scripts are rechecked. 11 9 12 **Prerequisites** 10 • SHARK-NIR connected to LBT network.11 • Automatic logging of the cryostat temperature 13 - SCICAM cooled down. 14 12 15 **Procedure** 13 • Run the cryostat warm up sequence 14 • Check how the system is performing every 30 minutes 16 - Repeat the science calibrations below (some of these are performed when SHARK-NIR was in the LBT cleanroom or at Padova cleanroom. Check [wiki:/docs/CommissioningPlan/P1.11 P1.11]) for details. 17 ||**Code**||**Activity**||**Location to perform this test**|| 18 ||SDC1||[wiki:/docs/CommissioningPlan/SDC1 Instrumental background for science]||Padova / LBT cleanroom / LBT Platform|| 19 ||SDC2||[wiki:/docs/CommissioningPlan/SDC2 Instrument flat field, detector linearity and bad pixels]||Padova / LBT cleanroom|| 20 ||SDC3||[wiki:/docs/CommissioningPlan/SDC3 Wavelength calibration]||Padova / LBT cleanroom?|| 21 ||SDC4||[wiki:/docs/CommissioningPlan/SDC4 Thermal background]||Padova / LBT cleanroom / LBT Platform|| 22 ||SDC5||[wiki:/docs/CommissioningPlan/SDC5 Detector gain]||Padova / LBT cleanroom / LBT Platform?|| 23 ||SDC6||[wiki:/docs/CommissioningPlan/SDC6 Detector persistence]||Padova / LBT cleanroom / LBT Platform?|| 24 ||SDC7||[wiki:/docs/CommissioningPlan/SDC7 Spectral resolution]||Padova / LBT cleanroom|| 25 ||SDC8||[wiki:/docs/CommissioningPlan/SDC8 Ghost calibration]||Padova|| 26 27 **Templates** 28 15 29 **Success criteria** 16 • Cryostat warmed up without any issues. 17 • The temperature at the detector is stable at dome temperature. 30 - All calibrations are successfully tested. 31 - All relevant information (files) are saved in the repository. 32 18 33 **Notes** 34 - The time dedicated to this activity has to be considered in combination with other activities. Parallelism is possible. 19 35 20 36 **LBTO support** 21 37 22 **Associated SHARK-NIR personnel**23 24 38 **Date performed and by whom**