wiki:docs/CommissioningPlan/P2.9

Version 10 (modified by kradhakrishnan, 4 years ago) (diff)

--

P2.9 Cryostat warm up check

  • Phase : 1
  • Status : Draft
  • Category : Daytime testing (functionality and operability) (C3)
  • Recurrence : at the end of every SHARK-NIR run?
  • Duration : 2 days

Description

  • Checking the cryostat warming up procedure.

Prerequisites

  • SHARK-NIR connected to LBT network.
  • Automatic logging of the cryostat temperature

Procedure

  • Run the cryostat warm up sequence
  • Check how the system is performing every 30 minutes

Success criteria

  • Cryostat warmed up without any issues.
  • The temperature at the detector is stable at dome temperature.

Notes

LBTO support

Associated SHARK-NIR personnel

Date performed and by whom