    1  == P2.8 Checking pointing offset between SHARK-NIR and SOUL-AO==
     1 == P2.8 Verification of the mask centering algorithm and final contrast with SOUL-AO and turbulence at ASM==
    22 
    33- **Phase**             :       2 
     
    55- **Category**  :       Daytime testing (functionality and operability) (C3) + Daytime calibration (C4)
    66- **Recurrence**        :       once at commissioning
    7 - **Duration**  :       1 day
     7- **Duration**  :       3 days
    88
    99**Description**
    10 - Test to check if there is a considerable pointing offset between the SHARK-NIR (SCICAM/TECCAM) and SOUL-AO as a function of the elevation of the telescope
     10- Verify the efficiency of the mask-centering algorithm and the final contrast with SOUL-AO and artificial turbulence intruded at the ASM.
    1111
    1212**Prerequisites**
     
    1414
    1515**Procedure**
    16 - TBD
     16- TBW
    1717
    1818**Templates**
    1919
    2020**Success criteria**
    21 - Estimate the pointing offset and conclude if it is acceptable or not. If not acceptable, take proper actions to overcome this issue.
     21- Final contrast produced for various seeing conditions matches the simulations.
    2222
    2323**Notes**