P2.5 SOUL AO system tests
- Phase : 2
- Status : Draft
- Category : Daytime testing (functionality and operability) (C2)
- Recurrence : after instrument installation at telescope platform
- Duration : 5 days
Description
- Proper working of the SOUL AO system is essential for the performance of the SHARK-NIR instrument. Arcetri team optimizes the SOUL AO system grabbing the PSF image from the SHARK-NIR SCICAM. Argos swing arm calibration light source will be used. If this is not available, RR may be used (second choice only).
Prerequisites
- SHARK-NIR active and working normally.
- Cryostat cold and SCICAM working properly.
- Activity P1.9 success criteria met.
- Telescope pointed to Zenith and permission to use the Argos swing arm calibration unit.
Procedure
- AO optimization procedure comes here
Success criteria
- SOUL AO system working in tandem with the SAHRK-NIR system.
- Acceptable improvement of the on-axis PSF (Argos Swing arm calibration light source) while SOUL AO is closed with known disturbances.
- Get a new and improved daytime telescope model for SHARK-NIR, if necessary.
Notes
LBTO support
- Authorize SHARK-NIR on SX side / Authorize mode to use the Argos Swing Arm
- Support from LBT SW Team, LBTI/Arcetri team.
Associated SHARK-NIR personnel
Date performed and by whom