P2.5 SOUL AO system test
- Phase : 2
- Status : Draft
- Category : Daytime testing (functionality and operability) (C3) + Daytime calibration (C4)
- Recurrence : after instrument installation at telescope platform
- Duration : 5 days
Description
- Proper working of the SOUL AO system is essential for the performance of the SHARK-NIR instrument. Arcetri team optimizes the SOUL AO system grabbing the PSF image from the SHARK-NIR SCICAM. The on-axis light source could be the Argos swing arm calibration light source, or one mounted on RR may be used (second choice only).
Prerequisites
- SHARK-NIR is active and working normally.
- Cryostat cold and SCICAM working properly.
- Activity P1.12 success criteria met.
- Telescope pointed to Zenith and permission to use the Argos swing arm calibration unit.
Procedure
- AO optimization procedure comes here
Templates
Success criteria
- SOUL AO system is working in tandem with the SHARK-NIR system.
- Acceptable improvement of the on-axis PSF (Argos Swing arm calibration light source) while SOUL AO is closed with known disturbances.
- If necessary, get a new and improved daytime telescope model for SHARK-NIR.
Notes
LBTO support
- Authorize SHARK-NIR on the SX side.
- Authorize mode to use the Argos Swing Arm. RR will be required on the SX side, if not the Argos swing arm.
- AO support.
Date performed and by whom