wiki:docs/CommissioningPlan/P2.5

Version 11 (modified by kradhakrishnan, 3 years ago) (diff)

--

P2.5 SOUL AO system test

  • Phase : 2
  • Status : Draft
  • Category : Daytime testing (functionality and operability) (C3) + Daytime calibration (C4)
  • Recurrence : after instrument installation at telescope platform
  • Duration : 5 days

Description

  • Proper working of the SOUL AO system is essential for the performance of the SHARK-NIR instrument. Arcetri team optimizes the SOUL AO system grabbing the PSF image from the SHARK-NIR SCICAM. The on-axis light source could be the Argos swing arm calibration light source, or one mounted on RR may be used (second choice only).

Prerequisites

  • SHARK-NIR is active and working normally.
  • Cryostat cold and SCICAM working properly.
  • Activity P1.12 success criteria met.
  • Telescope pointed to Zenith and permission to use the Argos swing arm calibration unit.

Procedure

  • AO optimization procedure comes here

Templates

Success criteria

  • SOUL AO system is working in tandem with the SHARK-NIR system.
  • Acceptable improvement of the on-axis PSF (Argos Swing arm calibration light source) while SOUL AO is closed with known disturbances.
  • If necessary, get a new and improved daytime telescope model for SHARK-NIR.

Notes

LBTO support

  • Authorize SHARK-NIR on the SX side.
  • Authorize mode to use the Argos Swing Arm. RR will be required on the SX side, if not the Argos swing arm.
  • AO support.

Date performed and by whom