P2.5 Cryostat Cooldown and Science detector calibrations

  • Phase : 2
  • Status : Draft
  • Category : Daytime testing (functionality and operability) (C3) + Daytime calibration (C4)
  • Recurrence : after instrument installation at telescope platform
  • Duration : 1 day

Description

  • At the beginning of the next run, the cryostat is cooled down and the science detector calibrations are performed (when at the telescope).

Prerequisites

Procedure

  • For the cryostat cool down, follow P1.4 and P1.5
  • For science detector calibrations follow P1.7

Templates

Success criteria

  • Cryostat cooled down.
  • SHARK-NIR working normally.
  • Science calibrations are performed and new values are saved.

Notes

  • Support from the Steward Observatory detector team.

LBTO support

  • Follow P1.4 and P1.5 (for the cryostat cool down)

Date performed and by whom