Version 12 (modified by kradhakrishnan, 3 years ago) (diff) |
---|
P2.5 Cryostat Cooldown and Science detector calibrations
- Phase : 2
- Status : Draft
- Category : Daytime testing (functionality and operability) (C3) + Daytime calibration (C4)
- Recurrence : after instrument installation at telescope platform
- Duration : 1 day
Description
- At the beginning of the next run, the cryostat is cooled down and the science detector calibrations are performed (when at the telescope).
Prerequisites
Procedure
- For the cryostat cool down, follow P1.4 and P1.5
- For science detector calibrations follow P1.7
Templates
Success criteria
- Cryostat cooled down.
- SHARK-NIR working normally.
- Science calibrations are performed and new values are saved.
Notes
- Support from the Steward Observatory detector team.
LBTO support
- Follow P1.4 and P1.5 (for the cryostat cool down)
Date performed and by whom