    44•       **Category**            :       Daytime testing (functionality and operability) (C2)   
    55•       **Recurrence**  :       after instrument installation at telescope platform
    6 •       **Duration**            :       2 hour(s)
     6•       **Duration**            :       5 days
    77**Description**
    8 •       Proper working of the SOUL AO system is essential for the performance of the SHARK-NIR instrument. We test the working of the SOUL AO system looking at the on-axis PSF (RR) with known disturbances running on the ASM. Also, we test the working of the new features - the waffle mode and inserting a static disturbance to the ASM.
     8•       Proper working of the SOUL AO system is essential for the performance of the SHARK-NIR instrument. Arcetri team optimizes the SOUL AO system grabbing the PSF image from the SHARK-NIR SCICAM. Argos swing arm calibration light source will be used. If this is not available, RR may be used (second choice only).
     9
    910**Prerequisites**
    10 •       RR mounted and SHARK-NIR aligned to telescope.
     11* SHARK-NIR active and working normally.
     12* Cryostat cold and SCICAM working properly.
     13* Activity [wiki:/docs/CommissioningPlan/P1.9 P1.9] success criteria met.
     14* Telescope pointed to Zenith and permission to use the Argos swing arm calibration unit.
     15
    1116**Procedure**
    12 •       a
    13 •       b
     17•       AO optimization procedure comes here
     18
    1419**Success criteria**
    1520•       SOUL AO system working in tandem with the SAHRK-NIR system.
    16 •       Acceptable improvement of the on-axis PSF (RR) while SOUL AO is closed with known disturbances.
     21•       Acceptable improvement of the on-axis PSF (Argos Swing arm calibration light source) while SOUL AO is closed with known disturbances.
    1722•       Get a new and improved daytime telescope model for SHARK-NIR, if necessary.
    18 •       Successfully running the waffle mode and setting a static shape on the ASM.
     23
    1924
    2025
    2126**Notes**
     27
    2228**LBTO support**
    23 •       Mount the RR on SX
     29•       Authorize SHARK-NIR on SX side / Authorize mode to use the Argos Swing Arm
    2430•       Support from LBT SW Team, LBTI/Arcetri team.
     31
    2532**Associated SHARK-NIR personnel**
    26 •       JF, LM, MdP, MM (from AZ)
     33
     34
    2735**Date performed and by whom**