wiki:docs/CommissioningPlan/P2.3

Version 7 (modified by mbergomi, 4 years ago) (diff)

--

P2.3 TCS communication test

  • Phase : 2
  • Status : Draft
  • Category : Daytime testing (functionality and operability) (C2)
  • Recurrence : after instrument installation at telescope platform
  • Duration : 1 day

Description

  • Communication with the LBT TCS is tested, with the aim to verify that the interface with TCS works as expected.

Prerequisites

  • All electronics and services up and running.

Procedure

  • Test all the TCS functionality needed by SHARK-NIR, which are detailed in AD2.
  • Check if the fits-writer is receiving all the right values from the LBT TCS.
  • Check if the derotator trajectory is received from the LBT TCS. The final testing of the trajectory with optical feedback will be done during the night time commissioning.

Success criteria

  • Connection to LBT TCS working well. All the test results are successful.
  • Fits-writer is receiving all the right values from LBT TCS.

Notes

LBTO support

  • Authorize SHARK-NIR, connecting to ASM+LBTI AO system
  • Permission to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the Fitswriter,
  • Support from the LBT SW team

Associated SHARK-NIR personnel

Date performed and by whom

Comments

MB: perhaps let's add here the check that SOUL can retrieve images from SCICAM

MB: also ADC trajectories might be tested here. Let's ask luca/Vale/depa

MB: add also sending presets to the telescope