P2.3 TCS communication test
- Phase : 2
- Status : Draft
- Category : Daytime testing (functionality and operability) (C2)
- Recurrence : after instrument installation at telescope platform
- Duration : 1 day
Description
- Communication with the LBT TCS is tested, with the aim to verify that the interface with TCS works as expected.
Prerequisites
- All electronics and services up and running.
Procedure
- Test all the TCS functionality needed by SHARK-NIR, which are detailed in AD2.
- Check if the fits-writer is receiving all the right values from the LBT TCS.
- Check if the derotator trajectory is received from the LBT TCS. The final testing of the trajectory with optical feedback will be done during the night time commissioning.
Success criteria
- Connection to LBT TCS working well. All the test results are successful.
- Fits-writer is receiving all the right values from LBT TCS.
Notes
LBTO support
- Authorize SHARK-NIR, connecting to ASM+LBTI AO system
- Permission to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the Fitswriter,
- Support from the LBT SW team
Associated SHARK-NIR personnel
Date performed and by whom
Comments
MB: perhaps let's add here the check that SOUL can retrieve images from SCICAM
MB: also ADC trajectories might be tested here. Let's ask luca/Vale/depa