Changes between Version 13 and Version 14 of docs/CommissioningPlan/P2.3


Ignore:
Timestamp:
04/22/22 19:12:48 (3 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P2.3

    v13 v14  
    2323**Success criteria**
    2424- Connection to LBT TCS is working well. All the test results are successful.
    25 - Fits-writer is receiving all the right values from LBT TCS.
     25- The fits-writer is receiving all the right values from LBT TCS.
    2626- SOUL can retieve the SCICAM image.
    2727
     
    2929- Arcetri Team remote support is required.
    3030- LBTI-AO team support is required.
     31- Note that although the actual work needs roughly about 2 days, a lot of it can go in parallel with other activites. So, for the estimation of the total days, only 1 day from here is considered.
    3132
    3233**LBTO support**
    33 
    3434- Authorize SHARK-NIR
    3535- Permission to use SX-ASM and LBTI-AO
    36 - Permission to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the Fitswriter,
     36- Permission to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the Fitswriter.
    3737- Support from the LBT SW team
    3838