Version 13 (modified by kradhakrishnan, 3 years ago) (diff) |
---|
P2.3 TCS communication test
- Phase : 2
- Status : Draft
- Category : Daytime testing (functionality and operability) (C3)
- Recurrence : after instrument installation at telescope platform
- Duration : 2 days
Description
- Communication with the LBT TCS is tested to verify that the interface with TCS works as expected.
Prerequisites
- All electronics and services are up and running.
Procedure
- Test all the TCS functionality (sending preset, ADC trajectory, etc.) needed by SHARK-NIR, detailed in AD2.
- Check if the fits-writer is receiving all the right values from the LBT TCS.
- Check if the derotator trajectory is received from the LBT TCS. The trajectory verification with optical feedback will be done during the nighttime commissioning.
- Re-check if SOUL can access the SCICAM image from the agreed-upon folder.
Templates
Success criteria
- Connection to LBT TCS is working well. All the test results are successful.
- Fits-writer is receiving all the right values from LBT TCS.
- SOUL can retieve the SCICAM image.
Notes
- Arcetri Team remote support is required.
- LBTI-AO team support is required.
LBTO support
- Authorize SHARK-NIR
- Permission to use SX-ASM and LBTI-AO
- Permission to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the Fitswriter,
- Support from the LBT SW team
Date performed and by whom