Changes between Version 12 and Version 13 of docs/CommissioningPlan/P2.3


Ignore:
Timestamp:
01/14/22 15:07:43 (3 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P2.3

    v12 v13  
    11== P2.3 TCS communication test ==
    2 •       **Phase**               :       2 
    3 •       **Status**              :       Draft   
    4 •       **Category**            :       Daytime testing (functionality and operability)  (C3)   
    5 •       **Recurrence**  :       after instrument installation at telescope platform
    6 •       **Duration**            :       2 days
     2
     3- **Phase**             :       2 
     4- **Status**            :       Draft   
     5- **Category**  :       Daytime testing (functionality and operability)  (C3)   
     6- **Recurrence**        :       after instrument installation at telescope platform
     7- **Duration**  :       2 days
     8
    79**Description**
    8 •       Communication with the LBT TCS is tested, with the aim to verify that the interface with TCS works as expected.
     10- Communication with the LBT TCS is tested to verify that the interface with TCS works as expected.
     11
    912**Prerequisites**
    10 •       All electronics and services up and running.
     13- All electronics and services are up and running.
     14
    1115**Procedure**
    12 •       Test all the TCS functionality (sending preset, ADC trajectory, etc.) needed by SHARK-NIR, which are detailed in AD2.
    13 •       Check if the fits-writer is receiving all the right values from the LBT TCS.
    14 •       Check if the derotator trajectory is received from the LBT TCS. The final testing of the trajectory with optical feedback will be done during the night time commissioning.
    15 * Re-check if SOUL can access the SCICAM image from the agreed-upon folder.
     16- Test all the TCS functionality (sending preset, ADC trajectory, etc.) needed by SHARK-NIR, detailed in AD2.
     17- Check if the fits-writer is receiving all the right values from the LBT TCS.
     18- Check if the derotator trajectory is received from the LBT TCS. The trajectory verification with optical feedback will be done during the nighttime commissioning.
     19- Re-check if SOUL can access the SCICAM image from the agreed-upon folder.
     20
     21**Templates**
     22
    1623**Success criteria**
    17 •       Connection to LBT TCS working well. All the test results are successful.
    18 •       Fits-writer is receiving all the right values from LBT TCS.
    19 * SOUL can retieve the SCICAM image.
     24- Connection to LBT TCS is working well. All the test results are successful.
     25- Fits-writer is receiving all the right values from LBT TCS.
     26- SOUL can retieve the SCICAM image.
     27
    2028**Notes**
     29- Arcetri Team remote support is required.
     30- LBTI-AO team support is required.
    2131
    2232**LBTO support**
    2333
    24 * Authorize SHARK-NIR
    25 * Permission to SX ASM and LBTI AO
    26 * Permission to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the Fitswriter,
    27 * Support from the LBT SW team
    28 
    29 **Associated SHARK-NIR personnel**
    30 * Arcetri Team
     34- Authorize SHARK-NIR
     35- Permission to use SX-ASM and LBTI-AO
     36- Permission to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the Fitswriter,
     37- Support from the LBT SW team
    3138
    3239**Date performed and by whom**
    33 
    34 **Comments**