P2.2 Instrument operability and functioning

  • Phase : 2
  • Status : Draft
  • Category : Daytime testing (functionality and operability) (C3)
  • Recurrence : once after instrument installation at telescope platform
  • Duration : 1 day

Description

  • The functionality and operability of individual components/sub-systems are tested. Verification of the internal alignment of the instrument is performed using the light source within. The final step is the performance of the system.

Prerequisites

  • All electronics and services are up and running.

Procedure

  • Initialize all the motors/sub-systems.
  • Check the functionality of all the motors (home position, named/nominal positions, and reaching software limits).
  • Check the working of all the light sources.
  • Using the on-axis diffraction-limited light source, check the internal alignment of the SHARK-NIR.
  • Check the relative positions of the coronagraphic masks.
  • Check for on-axis optical quality.

Templates

Success criteria

  • Motors and light sources are working as they should.
  • The internal alignment is preserved.
  • Performance of the system is acceptable.

Notes

LBTO support

Date performed and by whom