P2.0 SHARK-NIR Open Cart Activities
- Phase : 2
- Status : COMPLETE
- Category : Unpack, Assemble, Verification, and Installation (C1)
- Recurrence : once (unless deemed necessary to remove SHARK-NIR from the telescope platform)
- Duration : 1 day
Description
- All activities are to be done on the SHARK-NIR optical bench with the cart open.
Prerequisites
- electronics lab cleaned up by LBTO
Procedure
- For each rotatory stage, PI116.DGH:
- put two drops of Rodorsil 47V500 oil on the shaft of the filter wheels without dismounting anything. Make the mirror rotate a few times completely so that the oil distributes on the whole shaft.
- leave the C-RED2 ND filter wheel as last since it requires dismounting the folding mirror and the lens.
- Re-align both SCI filter wheels tilt to eliminate ghosts from flat field images.
- Install barometric pressure gauge (details to be added)
- clean the optical bench
Success criteria
- All activities successfully completed and tested the proper functioning,
Notes
- Activity in the LBT Electronic room.
LBTO support
Associated SHARK-NIR personnel
Date performed and by whom Minimum number of people available from SN team: 2+1 SW. Comments Luca to provide detail on oil and method to be used, if needed.