P2.0 SHARK-NIR Open Cart Activities

  • Phase : 2
  • Status : Draft
  • Category : Unpack, Assemble, Verification, and Installation (C1)
  • Recurrence : once (unless deemed necessary to remove SHARK-NIR from the telescope platform)
  • Duration : 1 day

Description

  • All activities to be done on the SHARK-NIR optical bench with the cart open.

Prerequisites

  • SHARK-NIR personnel present

Procedure

  • For each rotatory stage, PI116.DGH:
    • put 2 drops of oil.
    • leave the C-RED2 ND filter wheel as last since it requires dismounting the folding mirror and the lens.

Success criteria

  • All activities successfully completed and tested the proper functioning,

Notes

  • Activity in the LBT Electronic room.

LBTO support

Associated SHARK-NIR personnel

Date performed and by whom

Comments MB:in pre-requisites add that electronics lab needs to be cleaned by LBTO first. Luca to provide detail on oil and method to be used, if needed. MInimum number of people available dfrom SN team: 2+1 SW.