Version 15 (modified by mbergomi, 2 years ago) (diff) |
---|
P2.0 SHARK-NIR Open Cart Activities
- Phase : 2
- Status : Draft
- Category : Unpack, Assemble, Verification, and Installation (C1)
- Recurrence : once (unless deemed necessary to remove SHARK-NIR from the telescope platform)
- Duration : 1 day
Description
- All activities to be done on the SHARK-NIR optical bench with the cart open.
Prerequisites
- SHARK-NIR personnel present
Procedure
- For each rotatory stage, PI116.DGH:
- put 2 drops of oil.
- leave the C-RED2 ND filter wheel as last since it requires dismounting the folding mirror and the lens.
Success criteria
- All activities successfully completed and tested the proper functioning,
Notes
- Activity in the LBT Electronic room.
LBTO support
Associated SHARK-NIR personnel
Date performed and by whom
Comments MB:add the location: electronics laboratory, in pre-requisites, it needs to be cleaned by LBTO first. Luca to provide detail on oil and method to be used, if needed. MInimum number of people available dfrom SN team: 2+1 SW.