Changes between Version 2 and Version 3 of docs/CommissioningPlan/P2.0
- Timestamp:
- 01/15/21 19:55:27 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P2.0
v2 v3 2 2 • **Phase** : 2 3 3 • **Status** : Draft 4 • **Category** : Installation, integration, verification (C1)5 • **Recurrence** : once (the Installation of SHARK-NIR at the LBT platform)6 • **Duration** : 1 day for preparation, 1 day for installation , and 1 day contigency.4 • **Category** : Unpack, Assemble, Verification, and Installation (C1) 5 • **Recurrence** : once 6 • **Duration** : 2 days for preparation, 1 day for installation , and 1 day contingency. 7 7 **Description** 8 8 • Aligned SHARK-NIR is prepared for the Big-Lift and installed on the LBT platform. … … 20 20 • crane operators, mountain crew support for the lift-off and installation. 21 21 **Associated SHARK-NIR personnel** 22 • JF, LM, MdP, MM (from AZ) 22 23 23 **Date performed and by whom**