Changes between Version 2 and Version 3 of docs/CommissioningPlan/P2.0


Ignore:
Timestamp:
01/15/21 19:55:27 (4 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P2.0

    v2 v3  
    22•       **Phase**               :       2 
    33•       **Status**              :       Draft   
    4 •       **Category**            :       Installation, integration, verification (C1)                           
    5 •       **Recurrence**  :       once (the Installation of SHARK-NIR at the LBT platform)
    6 •       **Duration**            :       1 day for preparation, 1 day for installation , and 1 day contigency.
     4•       **Category**            :       Unpack, Assemble, Verification, and Installation (C1)   
     5•       **Recurrence**  :       once
     6•       **Duration**            :       2 days for preparation, 1 day for installation , and 1 day contingency.
    77**Description**
    88•       Aligned SHARK-NIR is prepared for the Big-Lift and installed on the LBT platform.
     
    2020•       crane operators, mountain crew support for the lift-off and installation.
    2121**Associated SHARK-NIR personnel**
    22 •       JF, LM, MdP, MM (from AZ)
     22
    2323**Date performed and by whom**