Version 3 (modified by kradhakrishnan, 4 years ago) (diff) |
---|
P2.0 Installation of SHARK-NIR at the LBT platform
- Phase : 2
- Status : Draft
- Category : Unpack, Assemble, Verification, and Installation (C1)
- Recurrence : once
- Duration : 2 days for preparation, 1 day for installation , and 1 day contingency.
Description
- Aligned SHARK-NIR is prepared for the Big-Lift and installed on the LBT platform.
Prerequisites
- SHARK-NIR aligned and ready for the lift-off.
Procedure
- Look at this document for the procedure and details.
Success criteria
- SHARK-NIR successfully installed at the LBT platform.
- Telescope is balanced.
- Connect all the cables and secure them.
- Reassure all the connections, nut and bolts etc.
Notes LBTO support
- crane operators, mountain crew support for the lift-off and installation.
Associated SHARK-NIR personnel
Date performed and by whom