wiki:docs/CommissioningPlan/P2.0

Version 3 (modified by kradhakrishnan, 4 years ago) (diff)

--

P2.0 Installation of SHARK-NIR at the LBT platform

  • Phase : 2
  • Status : Draft
  • Category : Unpack, Assemble, Verification, and Installation (C1)
  • Recurrence : once
  • Duration : 2 days for preparation, 1 day for installation , and 1 day contingency.

Description

  • Aligned SHARK-NIR is prepared for the Big-Lift and installed on the LBT platform.

Prerequisites

  • SHARK-NIR aligned and ready for the lift-off.

Procedure

  • Look at this document for the procedure and details.

Success criteria

  • SHARK-NIR successfully installed at the LBT platform.
  • Telescope is balanced.
  • Connect all the cables and secure them.
  • Reassure all the connections, nut and bolts etc.

Notes LBTO support

  • crane operators, mountain crew support for the lift-off and installation.

Associated SHARK-NIR personnel

Date performed and by whom