    1 == P2.0 Installation of SHARK-NIR at the LBT platform (will modify for cabling and check )==
     1== P2.0 Installation of SHARK-NIR at the LBT platform - 2==
    22•       **Phase**               :       2 
    33•       **Status**              :       Draft   
    4 •       **Category**            :       Unpack, Assemble, Verification, and Installation (C1)   
     4•       **Category**            :       Installation of SHARK-NIR at LBT platform (C2
    55•       **Recurrence**  :       once (unless deemed necessary to remove SHARK-NIR from the telescope platform)
    6 •       **Duration**            :       2 days for preparation, 1 day for installation , and 1 day contingency.
     6•       **Duration**            :       2 days.
    77**Description**
    8 •       Aligned SHARK-NIR is prepared for the Big-Lift and installed on the LBT platform.
     8•       Installation of the electronics cabinets, cabling, and confirming the safety & security of the instrument and area.
    99**Prerequisites**
    10 •       SHARK-NIR is aligned and ready for the lift-off.
     10•       SHARK-NIR (main parts) are installed on the LBTO platform (P2.0A).
    1111**Procedure**
    1212•       Look at AD4 document for the procedure and details.
     
    1616•       Connect all the cables and secure them.
    1717•       Reassure all the connections, nuts and bolts, etc.
     18* Confirm the safety and scuory of the instrument and the area.
    1819**Notes**
    19 Note that SHARK-NIR is NOT installed as a single piece. The cryostat has to be disassembled from bearing before the installation can start. Please look into the AD4 document for details.
     20Note that one (or two) rack(s) of the SHARK-NIR electronics are installed within the LBTO electronics cabinets (shared with LBTI and iLocater).
    2021
    2122**LBTO support**
    22 •       Crew members' support for the preparation, lift-off, and installation of SHARK-NIR
     23•       Crew members' support for the preparation, lift-off, and installation of SHARK-NIR electronics cabinet
    2324* Crane operator (mountain bay, LBT platform)
    2425* Safety officer
    2526* Working platform installed in front of the Gregorian focal-station SX,
    26 * Hatch door SX on the UIAP platform removed
    27 * Support for the installation of electronics in LBTI/SHARK cabinet
     27* Hatch door SX on the UIAP platform removed ???
    2828* kindly check the installation document for more details
    2929
     
    3434**Comments**
    3535
    36 MB: Please specify that Cryostat has to be disassembled from bearing before the installation can start. Put AD number instead of link.
    37 Concerning recurrence, in principle is only one, however optical bench only might have very low chances of being dismounted at some point for refurbishment of components which might be hard to happen in place
    38 
    3936LM: this seems to be a duplicate of 2.0A. Please check.