P2.0 Installation of SHARK-NIR at the LBT platform - 2

  • Phase : 2
  • Status : Draft
  • Category : Installation of SHARK-NIR at LBT platform (C2)
  • Recurrence : once (unless deemed necessary to remove SHARK-NIR from the telescope platform)
  • Duration : 2 days.

Description

  • Installation of the electronics cabinets, cabling, and confirming the safety & security of the instrument and area.

Prerequisites

  • SHARK-NIR (main parts) are installed on the LBTO platform (P2.0A).

Procedure

  • Look at AD4 document for the procedure and details.

Success criteria

  • SHARK-NIR successfully installed at the LBT platform.
  • Telescope is balanced.
  • Connect all the cables and secure them.
  • Reassure all the connections, nuts and bolts, etc.
  • Confirm the safety and scuory of the instrument and the area.

Notes Note that one (or two) rack(s) of the SHARK-NIR electronics are installed within the LBTO electronics cabinets (shared with LBTI and iLocater).

LBTO support

  • Crew members' support for the preparation, lift-off, and installation of SHARK-NIR electronics cabinet
  • Crane operator (mountain bay, LBT platform)
  • Safety officer
  • Working platform installed in front of the Gregorian focal-station SX,
  • Hatch door SX on the UIAP platform removed ???
  • kindly check the installation document for more details

Associated SHARK-NIR personnel

Date performed and by whom

Comments

LM: this seems to be a duplicate of 2.0A. Please check.