P2.0 Installation of SHARK-NIR at the LBT platform - 2
- Phase : 2
- Status : Draft
- Category : Installation of SHARK-NIR at LBT platform (C2)
- Recurrence : once (unless deemed necessary to remove SHARK-NIR from the telescope platform)
- Duration : 2 days.
Description
- Installation of the electronics cabinets, cabling, and confirming the safety & security of the instrument and area.
Prerequisites
- SHARK-NIR (main parts) are installed on the LBTO platform (P2.0A).
Procedure
- Look at AD4 document for the procedure and details.
Success criteria
- SHARK-NIR successfully installed at the LBT platform.
- Telescope is balanced.
- Connect all the cables and secure them.
- Reassure all the connections, nuts and bolts, etc.
- Confirm the safety and scuory of the instrument and the area.
Notes Note that one (or two) rack(s) of the SHARK-NIR electronics are installed within the LBTO electronics cabinets (shared with LBTI and iLocater).
LBTO support
- Crew members' support for the preparation, lift-off, and installation of SHARK-NIR electronics cabinet
- Crane operator (mountain bay, LBT platform)
- Safety officer
- Working platform installed in front of the Gregorian focal-station SX,
- Hatch door SX on the UIAP platform removed ???
- kindly check the installation document for more details
Associated SHARK-NIR personnel
Date performed and by whom
Comments
LM: this seems to be a duplicate of 2.0A. Please check.