Changes between Version 1 and Version 2 of docs/CommissioningPlan/P1.6
- Timestamp:
- 03/19/20 15:30:46 (5 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P1.6
v1 v2 6 6 • **Duration** : 8 hour(s) 7 7 **Description** 8 • Cool 8 • Cooldown the cryostat. 9 9 **Prerequisites** 10 10 • SHARK-NIR connected to LBT network. … … 17 17 **Success criteria** 18 18 • Cryostat cooled down without any issues. 19 • T emperature at the detector is stable at 77K ?19 • The temperature at the detector is stable at 77K ? 20 20 **Notes** 21 21 **LBTO support** 22 • Liquid Nitrogen refill ?22 • Liquid Nitrogen refill. Note that we do not mention about Liquid Nitrogen refill in any other place. This has to be done periodically every 24 hours. 23 23 **Associated SHARK-NIR personnel** 24 24 • JF, LM, MdP, MM(from AZ)