  • docs/CommissioningPlan/P1.6

    v1 v2  
    66•       **Duration**            :       8 hour(s)
    77**Description**
    8 •       Cool down the cryostat.
     8•       Cooldown the cryostat.
    99**Prerequisites**
    1010•       SHARK-NIR connected to LBT network.
     
    1717**Success criteria**
    1818•       Cryostat cooled down without any issues.
    19 •       Temperature at the detector is stable at 77 K ?
     19•       The temperature at the detector is stable at 77K ?
    2020**Notes**
    2121**LBTO support**
    22 •       Liquid Nitrogen refill?
     22•       Liquid Nitrogen refill. Note that we do not mention about Liquid Nitrogen refill in any other place. This has to be done periodically every 24 hours.
    2323**Associated SHARK-NIR personnel**
    2424•       JF, LM, MdP, MM(from AZ)