P1.6 Cool down the cryostat
- Phase : 1
- Status : Draft
- Category : Installation, integration, verification (C1)
- Recurrence : once
- Duration : 8 hour(s)
Description
- Cool down the cryostat.
Prerequisites
- SHARK-NIR connected to LBT network.
- Electronics cabinets on.
- Needs vacuum pumping at the beginning (vacuum pressure of 10e-5 is good, but the required amount is 10e-3 only.)
- Liquid nitrogen pumped?
Procedure
- Run the cryostat cooling down sequence
- Check how the system is performing every 30 minutes
Success criteria
- Cryostat cooled down without any issues.
- Temperature at the detector is stable at 77 K ?
Notes LBTO support
- Liquid Nitrogen refill?
Associated SHARK-NIR personnel
- JF, LM, MdP, MM(from AZ)
Date performed and by whom