     1== P1.6 Cool down the cryostat  ==
     2•       **Phase**               :       1 
     3•       **Status**              :       Draft   
     4•       **Category**            :       Installation, integration, verification (C1)                           
     5•       **Recurrence**  :       once
     6•       **Duration**            :       8 hour(s)
     7**Description**
     8•       Cool down the cryostat.
     9**Prerequisites**
     10•       SHARK-NIR connected to LBT network.
     11•       Electronics cabinets on.
     12•       Needs vacuum pumping at the beginning (vacuum pressure of 10e-5 is good, but the required amount is 10e-3 only.)
     13•       Liquid nitrogen pumped?
     14**Procedure**
     15•       Run the cryostat cooling down sequence
     16•       Check how the system is performing every 30 minutes
     17**Success criteria**
     18•       Cryostat cooled down without any issues.
     19•       Temperature at the detector is stable at 77 K ?
     20**Notes**
     21**LBTO support**
     22•       Liquid Nitrogen refill?
     23**Associated SHARK-NIR personnel**
     24•       JF, LM, MdP, MM(from AZ)
     25**Date performed and by whom**