Changes between Version 1 and Version 2 of docs/CommissioningPlan/P1.3
- Timestamp:
- 01/15/21 15:00:44 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P1.3
v1 v2 2 2 • **Phase** : 1 3 3 • **Status** : Draft 4 • **Category** : Installation, integration, verification (C1)4 • **Category** : Unpack, Assemble, Verification, and Installation (C1) 5 5 • **Recurrence** : once 6 • **Duration** : 4 hour(s)6 • **Duration** : half a day 7 7 **Description** 8 8 • Install and integrate the different SHARK-NIR opto-mechanical components onto the mechanical structure. Install the electronics cabinets. Move the unit to the cleanroom. … … 21 21 • 1-2 crew to support installation on the mechanical structure. 22 22 **Associated SHARK-NIR personnel** 23 • JF, LM, MdP, 23 24 24 **Date performed and by whom**