P1.3 Install the instrument in the cleanroom with its electronics cabinet
- Phase : 1
- Status : Draft
- Category : Installation, integration, verification (C1)
- Recurrence : once
- Duration : 4 hour(s)
Description
- Install and integrate the different SHARK-NIR opto-mechanical components onto the mechanical structure. Install the electronics cabinets. Move the unit to the cleanroom.
Prerequisites
- All the necessary tools and safety features to do the installation, integration, and moving to the cleanroom. The mechanical structure to hold SHARK-NIR at the cleanroom should be assembled and ready to be used (with the possibility to move to cleanroom).
Procedure
- Carefully assemble and integrate the various opto-mechanical components.
- Install them one by one onto the mechanical structure (either at mountain bay or at the clean room).
- Install the electronics cabinet.
Success criteria
- The SHARK-NIR is primarily assembled on to the mechanical structure.
- Electronics cabinets are installed.
Notes LBTO support
- Crane operator to lift and move stuff.
- 1-2 crew to support installation on the mechanical structure.
Associated SHARK-NIR personnel
- JF, LM, MdP,
Date performed and by whom
Attachments (7)
-
Shark-nir_ElectronicsRack_Padova.JPEG
(121.8 KB) -
added by kradhakrishnan 3 years ago.
Shark-nir_ElectronicsRack_Padova
-
Shark-Nir_CleanRoom_Space.jpg
(236.2 KB) -
added by kradhakrishnan 3 years ago.
Shark-Nir_CleanRoom_Padova_space
- Shark-Nir_CleanRoom_Space.2.jpg (235.8 KB) - added by kradhakrishnan 3 years ago.
-
SHARKNIR@LBTcleanroom.png
(235.2 KB) -
added by kradhakrishnan 3 years ago.
SHARKNIR@LBTcleanroom
- SHAR-NIR_remove_fan_over_DM_electronics.jpg (250.6 KB) - added by kradhakrishnan 3 years ago.
- SHARKNIR@LBTcleanroom_updated.png (221.3 KB) - added by kradhakrishnan 2 years ago.
- LBTO_rack.jpg (80.6 KB) - added by kradhakrishnan 2 years ago.
Download all attachments as: .zip