P1.3 Install the instrument in the cleanroom with its electronics cabinet

  • Phase : 1
  • Status : Draft
  • Category : Unpack, Assemble, Verification, and Installation (C1)
  • Recurrence : once
  • Duration : half a day

Description

  • Install and integrate the different SHARK-NIR opto-mechanical components onto the mechanical structure. Install the electronics cabinets. Move the unit to the cleanroom.

Prerequisites

  • All the necessary tools and safety features to do the installation, integration, and moving to the cleanroom. The mechanical structure to hold SHARK-NIR at the cleanroom should be assembled and ready to be used (with the possibility to move to cleanroom).

Procedure

  • Carefully assemble and integrate the various opto-mechanical components.
  • Install them one by one onto the mechanical structure (either at mountain bay or at the clean room).
  • Install the electronics cabinet.

Success criteria

  • The SHARK-NIR is primarily assembled on to the mechanical structure.
  • Electronics cabinets are installed.

Notes LBTO support

  • Crane operator to lift and move stuff.
  • 1-2 crew to support installation on the mechanical structure.

Associated SHARK-NIR personnel

Date performed and by whom